1. water pipes are up ... and boxed-up nicely
original (left) 10 Jun: new stainless pipes (center) 12 Jun: boxed up (right) |
2. aircon pipes are up ... trunking everywhere
some can be hidden
now you see it (left) and now you don't (right) |
storeroom |
wires, wires and wires ... for the db (left) lighting pt for dining (center) power pt for kitchen (right) |
study room - SCV cabling |
4. false ceilings are up
sooooooooo excited to see how the cove lights will turn out after installation
sooooooooo excited to see how the cove lights will turn out after installation
5. even parquet are laid in 1 day *wo* superman speed
16-Jun: master bedroom (left) study room (right) |
for the next few weeks, things will probably slow down now as they fabricate the carpentry off-site and until they obtain the approval to fix the "drain". but still will keep a lookout for surprise ;-)
2 comments:
Looks 70% done! Excited too to see the finished deco
barely 70% ley. probably another 3-4 weeks :( ... hope to post the final pic soon !!!