tiling work is scheduled for my house till end of may ... let's check out the progress after 1 week *grin*
18-May kitchen walls and toilet walls are first plastered with cement (or so i reckon ... )
 |
18-May (kitchen) |
 |
18-May (master bedroom bathroom) |
20-May walls tiles are "tiling"-up
 |
20-May (master bedroom bathroom) |
 |
20-May (kitchen) |
25-May TA DA ... wall tiles are done up for kitchen and bathroom
 |
25-May (kitchen) |
 |
25-May (kitchen side with cabinet) |
 |
25-May (kitchen rubbish chute) |
 |
25-May (master bedroom bathroom) |
ok dok. stay tune for the floor tiles :)