tiling work is scheduled for my house till end of may ... let's check out the progress after 1 week *grin*

18-May kitchen walls and toilet walls are first plastered with cement (or so i reckon ... )
18-May (kitchen)
18-May (master bedroom bathroom)











20-May walls tiles are "tiling"-up
20-May (master bedroom bathroom)
20-May (kitchen)




















25-May TA DA ... wall tiles are done up for kitchen and bathroom
25-May (kitchen)
25-May (kitchen side with cabinet)
25-May (kitchen rubbish chute)
25-May (master bedroom bathroom)
ok dok. stay tune for the floor tiles :)

Sunday, May 19, 2013

the walls are going down ....

hacking the walls down ...

step 1: educate the "hackers"

step 2: draw on the wall                                               step 3: hack it down !!!                                      
14-May-2013 (9:30pm)
15-May-2013 (9:07pm)
step 4: clear the haulage ... and it's done !
16-May-2013 (8:46pm)

Tuesday, May 14, 2013

let the drilling begins *SMILE*

my renovation is starting today ... check out the noise level :-p


so excited to check out the progress this weekend !!!